Where North Carolina has paused data centers
County and town actions on data centers: moratoriums adopted, ordinances passed, votes pending, and proposals rejected. Every row links to the meeting record or local report.
What the data shows
Local pauses on data centers spread quickly across North Carolina from late 2025 into 2026, mostly as twelve-month moratoriums while boards write zoning standards for the use. Some counties rejected a pause and some adopted an ordinance instead. A bill in the General Assembly proposed a two-year permit moratorium for the whole state and stalled in committee.
How to use it
Developers can see which jurisdictions have an active pause and which have written standards a project can meet. Reporters and planners can see the pattern by date. Landowners can see whether their county has acted.
How this dataset was built
Rows come from county and town meeting records, agendas, adopted ordinances, and local news reports of the votes. A row enters only when a public page confirms the action and the date. Moratoriums that cover only crypto mining are excluded. Actions we could not confirm on a live page are left out until we can.
Questions
Which North Carolina counties have a data center moratorium?
The table lists every county and town action we could confirm, with the date and the vote. Most adopted pauses run twelve months and expire on the anniversary of the vote unless extended.
Does a moratorium stop every data center?
No. A moratorium pauses new applications for the period the board sets. Projects already approved usually continue, and courts have exempted individual projects from a later pause.
Can I reuse this data?
Yes. The dataset is licensed CC BY 4.0. Cite FOUND and link to this page.
The data
| Jurisdiction | County | Date | Status | What happened | Sources |
|---|---|---|---|---|---|
| Raleigh | Wake | 2026-09 | proposed | Raleigh drafted a six-month data center moratorium in September 2026 with a council vote scheduled for October 6, 2026. | [9][24] |
| Nash County | Nash | 2026-09 | adopted | Nash County commissioners adopted on September 9, 2026 a moratorium on data centers and crypto mining in unincorporated areas until June 30, 2027. | [47] |
| Statesville | Iredell | 2026-09 | adopted | Statesville City Council unanimously adopted a 180-day data center moratorium effective September 14, 2026; previously approved projects are not affected. | [14][15] |
| Guilford County | Guilford | 2026-09 | debated | Guilford County commissioners voted September 17, 2026 to hold an October 15 hearing on a moratorium of up to 180 days. | [38] |
| Columbus County | Columbus | 2026-09 | debated | Columbus County scheduled an October 5, 2026 hearing on a 90- to 120-day data center moratorium. | [37] |
| Southport | Brunswick | 2026-09 | adopted | Southport's Board of Aldermen unanimously approved a 15-month data center moratorium on September 10, 2026. | [35] |
| Yadkin County | Yadkin | 2026-08 | adopted | Yadkin County commissioners voted 5-0 for a two-year data center moratorium in unincorporated areas in August 2026. | [45][46] |
| Cary | Wake | 2026-08 | adopted | Cary approved an 18-month data center moratorium on August 27, 2026. | [9][25] |
| Waxhaw | Union | 2026-08 | adopted | Waxhaw's Board of Commissioners unanimously approved a 12-month moratorium on data centers and crypto mining on August 11, 2026. | [21] |
| Randolph County | Randolph | 2026-08 | adopted | Randolph County commissioners amended the county data center ordinance to require closed-loop cooling and noise studies. | [17] |
| Farmville | Pitt | 2026-08 | adopted | Farmville commissioners unanimously adopted a 12-month data center moratorium in August 2026. | [54] |
| Greensboro | Guilford | 2026-08 | adopted | Greensboro City Council approved on August 18, 2026 a 180-day moratorium on data centers with power demand above 10 MW. | [16][17][18] |
| Edgecombe County | Edgecombe | 2026-08 | adopted | Edgecombe County approved a two-year data center moratorium on August 3, 2026, after adding data centers to its ordinance in November 2025. | [9][27] |
| Durham County | Durham | 2026-08 | adopted | Durham County commissioners voted 4-1 for a nine-month moratorium (to May 2027) on large data centers over 100,000 sq ft or using diesel backup or non-closed-loop cooling. | [22][9] |
| Fayetteville | Cumberland | 2026-08 | debated | Fayetteville City Council held an August 10, 2026 hearing on a data center moratorium without consensus and scheduled a special meeting for October 2026. | [9][29] |
| Whiteville | Columbus | 2026-08 | adopted | Whiteville City Council approved a 12-month moratorium on data centers and crypto mining from August 25, 2026 to August 25, 2027. | [36] |
| Alamance County | Alamance | 2026-08 | adopted | Alamance County commissioners voted 5-0 on August 17, 2026 for a 12-month moratorium on new data centers in unincorporated areas. | [19][20] |
| Surry County | Surry | 2026-07 | adopted | Surry County enacted a 60-day moratorium in June 2026 and a two-year data center moratorium in July 2026. | [42][43] |
| Mount Airy | Surry | 2026-07 | adopted | Mount Airy approved a 60-day moratorium on new data center projects on July 16, 2026. | [39] |
| Stokes County | Stokes | 2026-07 | rejected | Stokes County commissioners rejected a six-month data center moratorium in July 2026 after the planning board backed it. | [40][41] |
| Franklin | Macon | 2026-07 | adopted | Franklin Town Council unanimously approved a 12-month data center moratorium in July 2026. | [51][52] |
| Davie County | Davie | 2026-07 | adopted | Davie County commissioners unanimously approved a one-year data center moratorium in July 2026. | [44] |
| Davidson County | Davidson | 2026-07 | debated | Davidson County commissioners directed staff in July 2026 to draft a six-month data center moratorium, with a hearing set for August 24, 2026. | [39] |
| Holly Springs | Wake | 2026-06 | adopted | Holly Springs Town Council approved a moratorium of up to 12 months on data centers, data processing, and crypto mining in town limits and ETJ. | [26] |
| Hillsborough | Orange | 2026-06 | adopted | Hillsborough adopted a 60-day data center moratorium and extended it to one year after a June 22, 2026 hearing. | [49][50] |
| Charlotte | Mecklenburg | 2026-06 | adopted | Charlotte City Council unanimously approved a 150-day citywide data center moratorium on June 8, 2026, running through November 5, 2026. | [23] |
| Cumberland County | Cumberland | 2026-06 | adopted | Cumberland County adopted a six-month data center moratorium on June 15, 2026, expiring December 2026. | [9] |
| Asheville | Buncombe | 2026-06 | adopted | Asheville City Council unanimously approved a one-year moratorium on new data center development on June 23, 2026. | [30][31] |
| Boiling Spring Lakes | Brunswick | 2026-06 | adopted | Boiling Spring Lakes imposed a moratorium on data centers, data processing, and crypto mining from June 2, 2026 to no later than June 2, 2027. | [33][34] |
| Northampton County | Northampton | 2026-05 | adopted | Northampton County commissioners approved a 32-month data center moratorium on May 4, 2026. | [48] |
| Harnett County | Harnett | 2026-05 | adopted | Harnett County commissioners unanimously adopted a one-year data center moratorium on May 4, 2026, expiring May 3, 2027. | [28][9] |
| Durham | Durham | 2026-05 | adopted | The City of Durham adopted a 60-day data center moratorium on May 4, 2026 and extended it 10 months on June 15, 2026. | [9] |
| Woodfin | Buncombe | 2026-05 | adopted | Woodfin Town Council unanimously adopted a 12-month data center moratorium on May 19, 2026. | [32][30] |
| Statewide | statewide | 2026-04 | not enacted | House Bill 1189 (Datacenter Transparency Act) proposed a two-year statewide moratorium on data center siting permits from August 2026 but stalled in House Rules. | [56][57] |
| Watauga County | Watauga | 2026-04 | adopted | Watauga County commissioners unanimously passed a one-year data center moratorium on April 21, 2026. | [5] |
| Apex | Wake | 2026-04 | adopted | Apex approved a 12-month moratorium on data centers and crypto mining effective April 28, 2026, after the Natelli New Hill proposal was withdrawn. | [8][9] |
| Swain County | Swain | 2026-04 | adopted | Swain County commissioners unanimously approved a 12-month data center moratorium on April 21, 2026. | [10] |
| Rowan County | Rowan | 2026-04 | adopted | Rowan County commissioners unanimously approved a one-year moratorium on new data centers on April 20, 2026; the Long Ferry Road project is exempt under state law. | [11][12] |
| Orange County | Orange | 2026-04 | adopted | The Orange County Board of Commissioners voted 6-0 on April 21, 2026 for a one-year moratorium on large-scale data centers. | [13] |
| Lee County | Lee | 2026-04 | adopted | Lee County added data center standards to its development code on April 20, 2026 (pre-application meeting, noise study, utility confirmation). | [9] |
| Sanford | Lee | 2026-04 | adopted | Sanford added data centers to its development code on April 21, 2026. | [9] |
| Clyde | Haywood | 2026-04 | adopted | Clyde unanimously voted a one-year data center moratorium after an April 2026 hearing. | [53] |
| Boone | Watauga | 2026-03 | adopted | Boone unanimously approved a one-year moratorium on data centers and crypto mining on March 23, 2026. | [4] |
| Jackson County | Jackson | 2026-02 | adopted | Jackson County enacted a one-year moratorium on data center development in early February 2026. | [55] |
| Canton | Haywood | 2026-02 | adopted | Canton's Board of Aldermen unanimously passed a 12-month moratorium on data centers, server farms, and crypto mines on February 11, 2026. | [3] |
| Kings Mountain | Cleveland | 2026-02 | adopted | Kings Mountain approved a six-month moratorium on new data centers on February 26, 2026; council debated a 12-month extension in July 2026. | [6][7] |
| Chatham County | Chatham | 2026-02 | adopted | Chatham County adopted a 12-month moratorium on data centers, data processing, and crypto mining, effective until February 11, 2027; a judge later exempted the Eco TIP West project. | [1][2] |
| Wendell | Wake | 2026 | adopted | Wendell adopted a data center pause through December 31 with no applications pending. | [9] |
| Black Mountain | Buncombe | 2026 | adopted | Black Mountain approved new zoning standards for data centers. | [32][30] |
Cite this dataset
FOUND, "Where North Carolina has paused data centers", lotsfound.com, 2026. Data from public sources listed below. Licensed CC BY 4.0.
Free to reuse with attribution to FOUND and a link to this page (CC BY 4.0).
Sources
- wral.com
- ncnewsline.com
- wunc.org
- wunc.org
- wataugademocrat.com
- wfae.org
- cardinalpine.com
- abc11.com
- wral.com
- bpr.org
- wbtv.com
- wfae.org
- orangecountync.gov
- wbtv.com
- statesvillenc.net
- whqr.org
- wfdd.org
- ncnewsline.com
- alamancenews.com
- hawriver.org
- wbtv.com
- wunc.org
- wfae.org
- wfae.org
- govtech.com
- wral.com
- bisnow.com
- sanfordherald.com
- cityviewnc.com
- wlos.com
- foxcarolina.com
- mountainx.com
- cityofbsl.org
- wect.com
- wect.com
- wect.com
- borderbelt.org
- rhinotimes.com
- wfae.org
- wfae.org
- wfae.org
- wfae.org
- wfae.org
- wunc.org
- yadkinripple.com
- wfae.org
- rockymounttelegram.com
- northcarolinahealthnews.org
- chapelboro.com
- chapelboro.com
- thefranklinpress.com
- hoodline.com
- themountaineer.com
- witn.com
- theucnow.com
- lrs.sog.unc.edu
- carolinajournal.com