# Data-center site selection: the criteria, in the order they end sites

Local permission, power, and usable connected land decide whether a data-center site works. Check those first. The later questions deserve time only if the site survives them.

[Start a data-center search](/services/data-center-sites/)

In this article

1. [Why order matters](#why-order-matters)
2. [1. Can it be approved here?](#1-can-it-be-approved-here)
3. [2. Is there a path to power?](#2-is-there-a-path-to-power)
4. [3. Who are the neighbors?](#3-who-are-the-neighbors)
5. [4. Is there enough usable, connected land?](#4-is-there-enough-usable-connected-land)
6. [5. Water, wastewater, and fire protection](#5-water-wastewater-and-fire-protection)
7. [6. Fiber](#6-fiber)
8. [7. Ground conditions](#7-ground-conditions)
9. [8. Environmental history and conservation interests](#8-environmental-history-and-conservation-interests)
10. [9. Roads and heavy-haul access](#9-roads-and-heavy-haul-access)
11. [10. Taxes and incentives](#10-taxes-and-incentives)
12. [What the public record shows for each criterion](#what-the-public-record-shows-for-each-criterion)
13. [Two questions a checklist leaves out](#two-questions-a-checklist-leaves-out)
14. [Key recap](#key-recap)
15. [Questions](#questions)
16. [References](#references)

> **Quick summary:** This guide lists what decides a data-center site, in the order sites usually fail. It is for buyers, developers, and landowners who screen land in North Carolina. Check local permission, power, and usable connected land first; the later criteria deserve time only on sites that survive those.

## Why order matters

A site can score well on nine factors and fail on one. If that one is a local pause or a power dead end, the other nine were wasted effort. We check the deal-ending questions first and spend the detailed work only on sites that survive them. See [Why data-center sites get rejected](/insights/why-sites-get-rejected/).

## 1. Can it be approved here?

Find the government that regulates the parcel. Read its use table, required approvals, and any board action that pauses data centers. A county and a town inside it can give different answers. North Carolina’s [zoning law](https://www.ncleg.gov/EnactedLegislation/Statutes/HTML/BySection/Chapter_160D/GS_160D-702.html) gives local governments zoning authority. Its [moratorium law](https://www3.ncleg.gov/EnactedLegislation/Statutes/HTML/BySection/Chapter_160D/GS_160D-107.html) sets the rules for a local pause. See [How to read a data-center moratorium](/insights/reading-a-data-center-moratorium/) and [A zoning label is only the beginning](/what-we-check/zoning-and-moratoriums/).

## 2. Is there a path to power?

The relationship of the tract to high-voltage transmission and substations, the serving utility, and the obstacles to a connection. Then the questions only the utility can answer: capacity, upgrades, cost, schedule, and a second feed. See [A substation next door is not power](/insights/power-proximity-is-not-capacity/).

## 3. Who are the neighbors?

Homes, schools, and places of worship nearby, and how this community has treated earlier proposals. See [The neighbors decide more sites than the zoning map](/insights/neighbors-and-public-opposition/).

## 4. Is there enough usable, connected land?

Acreage after floodplain, wetlands, stream buffers, slopes, and easements, and whether what remains is in one workable piece. Then whether the site can expand. See [Gross acres are not usable acres](/what-we-check/flood-wetlands-soils/).

> **The short version:** The first three questions end the most sites. A local pause, no path to power, or a community that has turned down earlier proposals can make the rest of the checklist irrelevant.

## 5. Water, wastewater, and fire protection

Who could serve the site, what they report about supply and treatment, and what the provider must confirm. The cooling design changes how much this matters. See [A water system nearby is not water for your project](/what-we-check/water-and-sewer/).

## 6. Fiber

Providers on record, nearby interconnection points, and whether separate routes are truly separate. See [Fiber nearby is not fiber to the site](/what-we-check/fiber/).

## 7. Ground conditions

Soils, rock, groundwater, and slope, at the level public surveys allow. These decide cost more often than feasibility.

## 8. Environmental history and conservation interests

What has been recorded on and near the land, and any conservation easement that limits use. See [The land has a history. The records hold part of it.](/what-we-check/environmental-records/).

> **Take action:** If you are screening several tracts, ask for a short list read in this order. Start with [Sites a data-center buyer can act on](/services/data-center-sites/).

## 9. Roads and heavy-haul access

The roads in, bridges and weight postings on the route, and whether a [driveway permit](https://connect.ncdot.gov/resources/safety/Teppl/TEPPL%20All%20Documents%20Library/A-21_code.pdf) is likely. See [A road beside the land is not a way in](/what-we-check/access-and-roads/).

## 10. Taxes and incentives

State and local programs can change operating cost for the life of the campus. They rarely rescue a site that fails on the first three.

## What the public record shows for each criterion

Each criterion has a public record that starts the answer and a professional who finishes it. The record tells you which question to ask. It rarely closes the question on its own.

| Criterion | Where the public record starts | Who confirms |
|---|---|---|
| Local approval | The use table, the zoning map, and board minutes | County or town planning staff, in writing |
| Power | Line and substation maps, and the state's [electric service area law](https://www.ncleg.gov/EnactedLegislation/Statutes/HTML/BySection/Chapter_62/GS_62-110.2.html), which ties service rights to the premises | The serving utility |
| Usable land | [FEMA flood maps](https://msc.fema.gov/portal/home) and the [federal wetlands mapper manual](https://www.fws.gov/sites/default/files/documents/Wetlands-Mapper-Documentation-Manual-May-2019.pdf) | A licensed surveyor and a wetland delineation |
| Ground conditions | The [Web Soil Survey](https://websoilsurvey.nrcs.usda.gov/app/) | A geotechnical engineer |
| Access | NCDOT road and driveway rules | NCDOT district staff and a professional engineer |

Each source states its own limits. FEMA calls its Map Service Center the official public source for flood hazard information under the National Flood Insurance Program, and it updates the maps over time. The wetlands mapper uses a biological definition of wetlands. It does not set the reach of any regulatory program, and the agency refers you to the Corps of Engineers before you disturb wetlands. The soil survey says some uses need an onsite investigation. Read each source for what it is, then hand the open question to the person who answers it. See [What desktop research can tell you, and who answers the rest](/insights/what-desktop-research-cannot-replace/).

## Two questions a checklist leaves out

**Is the land actually available, and who can sell it?** Suitability and availability are separate facts. A perfect tract with five heirs and no agreement is not a site yet.

**Who is the buyer?** The same land reads differently to an operator that will hold it and a developer that will prepare and sell it. See [Who buys data-center land, and what each buyer needs](/insights/data-center-buyer-types/).

## Key recap

- Check the questions that end sites first: local approval, a path to power, and the neighbors.
- North Carolina law gives local governments zoning authority and sets the rules for a local moratorium.
- A nearby line or substation starts the power question; the utility answers capacity, upgrades, cost, schedule, and a second feed.
- Usable, connected acreage after floodplain, wetlands, stream buffers, slopes, and easements matters more than gross acreage.
- Taxes and incentives change operating cost but rarely rescue a site that fails on the first three.
- Suitability and availability are separate facts, and the buyer type changes how the same land reads.

## Questions

### What is the most important factor in data-center site selection?

Power, in the sense of a utility's ability to deliver the load on the project's schedule. In practice a local government's position can end a site even sooner.

### How long does site selection take?

Desktop screening of a candidate takes days. Utility studies, approvals, and engineering take months to years. Screening exists to make sure those months are spent on the right land.

## References

Primary sources cited on this page, in APA style.

- 19A N.C. Admin. Code 2B.0601-.0604 (2020). [https://connect.ncdot.gov/resources/safety/Teppl/TEPPL%20All%20Documents%20Library/A-21_code.pdf](https://connect.ncdot.gov/resources/safety/Teppl/TEPPL%20All%20Documents%20Library/A-21_code.pdf)
- Federal Emergency Management Agency. (n.d.). *FEMA Flood Map Service Center*. Retrieved October 3, 2026, from [https://msc.fema.gov/portal/home](https://msc.fema.gov/portal/home)
- N.C. Gen. Stat. § 160D-107 (2025). [https://www3.ncleg.gov/EnactedLegislation/Statutes/HTML/BySection/Chapter_160D/GS_160D-107.html](https://www3.ncleg.gov/EnactedLegislation/Statutes/HTML/BySection/Chapter_160D/GS_160D-107.html)
- N.C. Gen. Stat. § 160D-702 (2025). [https://www.ncleg.gov/EnactedLegislation/Statutes/HTML/BySection/Chapter_160D/GS_160D-702.html](https://www.ncleg.gov/EnactedLegislation/Statutes/HTML/BySection/Chapter_160D/GS_160D-702.html)
- N.C. Gen. Stat. § 62-110.2 (2025). [https://www.ncleg.gov/EnactedLegislation/Statutes/HTML/BySection/Chapter_62/GS_62-110.2.html](https://www.ncleg.gov/EnactedLegislation/Statutes/HTML/BySection/Chapter_62/GS_62-110.2.html)
- U.S. Department of Agriculture, Natural Resources Conservation Service. (n.d.). *Web Soil Survey*. Retrieved October 3, 2026, from [https://websoilsurvey.nrcs.usda.gov/app/](https://websoilsurvey.nrcs.usda.gov/app/)
- U.S. Fish and Wildlife Service. (2019, April). *Wetlands mapper documentation and instructions manual*. [https://www.fws.gov/sites/default/files/documents/Wetlands-Mapper-Documentation-Manual-May-2019.pdf](https://www.fws.gov/sites/default/files/documents/Wetlands-Mapper-Documentation-Manual-May-2019.pdf)

## Data-center site selection

- [Sites a data-center buyer can act on](/services/data-center-sites/)
- [Who buys data-center land, and what each buyer needs](/insights/data-center-buyer-types/)
- [What a good site summary contains](/insights/what-a-site-summary-contains/)
- [Why data-center sites get rejected](/insights/why-sites-get-rejected/)
- [Land feasibility study: what it covers and when to order one](/insights/land-feasibility-study/)
- [What desktop research can tell you, and who answers the rest](/insights/what-desktop-research-cannot-replace/)
- [When a warehouse is a data-center site](/insights/industrial-conversion-sites/)
- [Data center real estate: how the land market works](/insights/data-center-real-estate/)
- [What is a powered shell data center?](/insights/powered-shell-data-center/)
- [From a parcel number to a site a buyer can act on](/how-it-works/)

Send the requirements. We reply with how we would run the search.

[Start a data-center search](/services/data-center-sites/)

## Tell us what the project needs

Load, acreage, counties, and timeline. We reply with how we would run the search and where we would start.